Severn Trent (LON:SVT) said it remains confident in its operational and financial guidance as it increases investment in its water and wastewater network, while warning that debt costs are likely to rise.
Chief Executive James Jesic said the company delivered £1 billion of capital investment in the first six months of the financial year, up 40% from the same period a year earlier. That brought investment to £3 billion for the current asset management period, known as AMP8.
Jesic said Severn Trent expects to have about 80% of its AMP8 program under contract by the end of the financial year. He also reaffirmed guidance for £50 million of outcome delivery incentives, or ODIs, in the current financial year and £300 million by the end of the AMP period, including both ODIs and price control deliverables.
Investment and regulatory outlook
Jesic identified climate change, population growth and tightening environmental legislation as long-term drivers of investment. He said the Midlands population is expected to grow by 12% by 2050, requiring additional water sources and wastewater treatment capacity.
Director of Strategy and Regulation Shane Anderson said the company’s PR24 regulatory settlement provided £15 billion of investment. He said Severn Trent would like to see more investment in asset health, clearer resilience standards and a more focused set of priorities for the next price review, PR29.
Anderson said discussions with regulator Ofwat on the PR29 methodology had been constructive. While some performance outcomes are expected to be consolidated, he said at least 10 would remain in place.
Jesic said the company had secured £402 million in the first year of the regulatory “reopener” process, including £51 million of in-period funding, although the determination remained at the draft stage. Reopeners allow companies to seek adjustments to investment plans during a regulatory period.
For future submissions, Anderson highlighted rising sewer mains, large-diameter water mains and investments to accommodate population growth. Jesic said the company would provide more insight into its potential second-year plans alongside its final results in May.
Efficiency gains and funding costs
Severn Trent has delivered £300 million of efficiencies so far against guidance for £650 million over the AMP period, Jesic said. Capital Delivery Director Paul Baxter said £250 million of the savings were capital efficiencies, citing standardized electrical control panels as one example of reduced procurement, design and construction costs.
Jesic said the savings give the company choices about reinvestment and help offset cost pressures. He added that Severn Trent had been able to fund its first-year reopener investment without additional borrowing.
Chief Financial Officer Helen Miles said debt costs were expected to rise in the second half, partly because of inflation on index-linked debt and the higher cost of new borrowing. She said the company had broadened its financing sources to include euro markets, Asia and Swiss private placements, and remained confident in demand for its debt.
Miles also said she expected some outperformance on power costs relative to the relevant index, given the prices at which the company had locked in energy. Severn Trent plans to share figures against cost indices as the AMP progresses, she said.
Jesic confirmed that Miles would leave the company after 12 years and said a process was underway to find her successor. No departure date was given on the call.
ODI discussions and environmental performance
Severn Trent is contesting elements of Ofwat’s draft determination on its ODI rewards. Anderson said the difference between the company’s calculation and Ofwat’s included a biodiversity measure, for which the regulator had raised questions about how sites were assessed.
Anderson said Severn Trent used satellite technology to establish a baseline and had provided evidence that it visited 97% of the relevant sites. He also said an outcome adjustment mechanism had been recorded at £4 million in the company’s document but should amount to £17 million. The final determination is expected on Dec. 15, Jesic said.
Despite those discussions, Jesic said the company’s ODI guidance was unchanged. He also said Severn Trent was maintaining its existing earnings-per-share guidance, without providing a figure on the call.
The company received a four-star environmental performance assessment rating for a seventh consecutive year, Jesic said. He cautioned that changes to the Environment Agency’s methodology, including the addition of some incidents previously classified as causing no harm and third-party pollution, would increase reported sector totals.
Jesic said Severn Trent had spent £400 million on pollution-related work and achieved a 44% reduction on a like-for-like basis. Director of Customer Operations Steph Cawley said the company was focusing on prevention and on problem asset classes, including rising mains and pumping stations.
Customer support
As investment adds pressure to bills, Severn Trent has allocated a further £25 million to provide £100 bill credits to more than 200,000 customers who may narrowly miss out on existing support, Director of Customer Solutions and Technology Jude Burditt said.
Burditt said the company had already committed £575 million of support during the current AMP, covering one in six families in its region. Jesic said the company was also discussing ways to deliver environmental benefits at lower cost while meeting investment requirements.
About Severn Trent (LON:SVT)
As one of Britain’s largest water companies, we supply fresh, clean drinking water to over nine million people across our region – around two billion litres every day. Once used, we collect, clean, and treat the water before safely returning it to the environment. We are one of only three listed water stocks in the UK, offering a valuable combination of reliable earnings, long-term asset growth, and inflation-linked dividends. The UK’s regulatory model provides a high degree of certainty over five-year periods.